Direct Administrative Costs (DAC) in Public Assistance
A plain-language overview of direct administrative costs: what FEMA's guide and policy mean by them, how they came to sit inside the management cost contribution, and how they differ from the cost of managing the project itself.
FEMA policy changes; check the cited source for your declaration.
Direct administrative costs, usually shortened to DAC, are the administrative costs an applicant can tie to one specific Public Assistance project — staff time spent inspecting that project's sites, writing up its damage, assembling its paperwork and moving it through FEMA's review. For years they were claimed project by project. For most current disasters they are claimed instead as part of a capped management cost contribution, under a change to the Stafford Act made in 2018 and a FEMA policy that implements it. This page describes that arrangement as FEMA's Public Assistance Program and Policy Guide (PAPPG) and FEMA's Public Assistance Management Costs policy set it out. The guide is Version 5.0 Amended, which applies to disasters declared on or after January 6, 2025; an older declaration follows the edition in force when it was declared.
What the term means
The Stafford Act, as amended by the Disaster Recovery Reform Act of 2018, defines a management cost as any indirect cost, any direct administrative cost and any other administrative expense associated with a specific project. FEMA's guide and its policy use materially the same definition for Public Assistance. What distinguishes a direct administrative cost from an indirect one is whether it can be assigned to a particular project: the guide describes an indirect cost as one incurred for a common purpose that benefits more than one project and cannot readily be assigned to any one of them, while DAC is the administrative work that can be.
FEMA's policy lists the kinds of activity it has in mind: preliminary damage assessments, meetings about the program or the overall claim, grouping damage sites and preparing correspondence, site inspections and travel, writing detailed damage descriptions, evaluating hazard mitigation measures, preparing projects and reviewing project worksheets, collecting and submitting documents, requesting payment, and training.
Inside the management cost contribution
Under FEMA's policy, management costs — DAC included — are not claimed as line items on each project. They are grouped into a single project of their own, which FEMA calls Category Z, and reimbursed at actual cost up to a percentage of the applicant's total award: one rate for the recipient (usually the state, territory or Tribal Nation that administers the grant) and a lower one for each subrecipient. The contribution is funded entirely by the federal government, with no state or local share. Our page on management costs describes that contribution — how the percentage is calculated, when the costs may be incurred and how the final amount is reconciled.
Which framework applies depends on when the disaster was declared. FEMA's policy applies to disasters and emergencies declared on or after August 1, 2017, and it is the only framework for declarations on or after October 5, 2018; for the declarations in between, applicants that were already claiming DAC the older way could choose to keep doing so or to switch, by a deadline that has long passed. Earlier declarations stay under the earlier rules, which is one reason the edition of FEMA's guide that applies to a disaster matters — see which PAPPG version applies.
Administering the grant, or managing the project
The distinction that matters most in practice is between management costs and the cost of managing the project itself. FEMA's guide draws the line by asking whether the work would be needed regardless of Public Assistance. Project management — procurement, legal review of contracts, monitoring the contractor, construction oversight and inspections, environmental and historic preservation studies, permits, and the load tickets of a debris operation — is work the applicant would do anyway, and the guide treats it as a direct cost of the project, eligible when it is tracked and tied to a specific eligible project, with no percentage cap and the project's own cost share. Architectural, engineering and design services for the approved scope of work belong to the project in the same way. Management costs, by contrast, are the costs of receiving and administering the funding: preparing the claim, documenting it, asking for payment.
The line runs the other way too. FEMA's guide treats the costs of assessing a disaster's overall impact, locating damage and conducting preliminary damage assessments as management costs rather than project costs; once damage has been identified, the detailed inspections needed to decide the extent of the damage and the method of repair belong to the project, prorated where only part of a system was damaged.
What the records are expected to show
FEMA's guide and its policy describe the documentation that supports a management cost claim: a summary of the work performed and the costs claimed, including the number of employees, the equipment used and its rates, the hours of labor and equipment, the total costs and a general description of the tasks each person performed; the underlying cost records, such as payroll data, procurement records, contracts and invoices, with an explanation of the activities; and support for the reasonableness of the costs. The policy notes that FEMA may ask for more and that it makes the final decision on eligibility and reasonableness. Interim obligations of the contribution are provisional, and the final amount is reconciled to the actual, reasonable costs the records support.
Where the rules live
Three documents carry the rules: Section 324 of the Stafford Act, FEMA's Public Assistance Management Costs policy with its standard operating procedures, and the cost eligibility chapter of FEMA's guide. Because the framework turned on the declaration date and the policy was issued as an interim one, the details for a specific disaster are best confirmed against those documents and with FEMA or the recipient; our page on the building blocks of eligibility describes how costs fit into the wider eligibility framework.
This page is a starting point, not the policy. For a question about your own disaster, ask PAPPAIA with your declaration date. Answers are grounded in cited policy sources and include exact references for independent verification — free during the public preview.
Ask PAPPAIAFrequently asked questions
Is DAC still claimed on individual project worksheets?
Not for disasters declared on or after October 5, 2018. Under FEMA's management costs policy, direct administrative costs are part of a single management cost contribution, claimed through one project per applicant and funded entirely by the federal government. Project-level DAC continues only for certain older declarations, where applicants kept the earlier approach.
What is the difference between DAC and management costs?
Management cost is the wider term: the Stafford Act defines it as any indirect cost, any direct administrative cost and any other administrative expense associated with a specific project. DAC is the part that can be assigned to a particular project. Under current policy both are reimbursed together through the capped contribution.
Are engineering, design and construction oversight costs DAC?
No. FEMA's guide treats project management and design services — procurement, contract review, monitoring the contractor, construction oversight, permits, and architectural and engineering design — as direct costs of the project itself, because they would be needed regardless of Public Assistance. Management costs, DAC included, cover the work of receiving and administering the funding.
Are damage assessment costs project costs?
As a rule, no. FEMA's guide treats the costs of assessing a disaster's overall impact, locating damage and conducting preliminary damage assessments as management costs. Once damage has been identified, the detailed inspections needed to decide its extent and the method of repair belong to the project, prorated where only part of a system was damaged.
Sources
- FEMA Recovery Policy FP 104-11-2, Public Assistance Management Costs (Interim) — definitions, applicability and the transition elections, the management cost contribution, eligible activities, documentation
- FEMA, Public Assistance Management Costs Standard Operating Procedures (February 2019) — the election deadline, the period of performance and the final claim
- Stafford Act § 324 (42 U.S.C. § 5165b) — the definition of management costs and the Public Assistance rates
- PAPPG v5, Chapter 6: Cost Eligibility — Project Management and Design Services; Grant Management and Administration; Surveys to Assess or Locate Damage — PDF pp. 113-114
- PAPPG v5, Chapter 5: Damage and Impact Information — management costs on the impact list; the grant management grouping — PDF pp. 74, 78
- PAPPG v5, Appendix: Glossary — management cost — PDF p. 274
Found an error, or something that has changed? Tell us.
Disclaimer. This page is educational material and may be outdated or incorrect. It is not FEMA guidance, not legal or professional advice, and not a substitute for the FEMA documents it cites; PAPPAIA is not affiliated with or endorsed by FEMA or any government agency. Before you act, read the cited source for your declaration and confirm with your FEMA regional contact or your recipient.